Utility Coordination

Pepco service upgrade, WASA, Washington Gas, and all utility applications for 6100 Chillum

Total Items
5
Blocked
0
Complete
0

2 critical-path utility items still pending — these may delay construction milestones.

DCRABuilding Permit — Cultivation Facility TIIN PROGRESSCritical Path

Tenant improvement permit for full facility buildout. Includes structural, MEP, and use change to cannabis cultivation.

Est: $8,500
PepcoCommercial Service UpgradeNOT STARTEDCritical Path

Upgrade electrical service to support cultivation facility load — LED lighting, HVAC, irrigation pumps. Estimated 400-600A 3-phase service required.

Est: $25,000
DC WaterCommercial Meter UpgradeNOT STARTED

Upgrade water meter to support irrigation system demand. RO system + irrigation = significant daily water usage.

Est: $3,500
Verizon / ComcastBusiness Fiber InstallationNOT STARTED

High-speed fiber internet for security camera system, METRC connectivity, remote monitoring of environmental controls.

Est: $1,200
Washington GasService VerificationNOT STARTED

Verify existing gas service capacity for HVAC backup heating. Confirm no upgrade needed.

0