Project Tracker

89 tasks across 13 phases

89
Total
0
Complete
11
In Progress
0
Blocked
0
Overdue
47
Critical
Pre-Construction & Due DiligenceIN PROGRESS

Asbestos/lead survey, Phase I ESA, zoning confirmation, as-built field walk, design team engagement. Section 12.4.

0/8 (0%)
Engage industrial hygienist — asbestos/lead survey

Required before any drilling, cutting, or penetrations. 2-3 week turnaround. Engage IH before fit-out work begins. Section 12.4.

CRITICALIN PROGRESS
60%
Field walk as-builts with Cornerstone Architecture

HO + Cornerstone walk all spaces. Confirm dimensions, identify conflicts, lock penetration locations. Open Item #7.

CRITICALIN PROGRESS
40%
Confirm zoning — cannabis cultivation at 6100 Chillum Place NE

Confirm with compliance counsel before permit applications filed. Open Item #88.

CRITICALNOT STARTED
Phase I Environmental Site Assessment

Recommended before lease execution or purchase commitment. Section 12.4.

HIGHNOT STARTED
Roof membrane assessment + solar panel field verify

Assess existing roof condition before placing condensing units. 206 solar panels confirmed from drawings — field verify exact locations before any rooftop equipment placed. Open Items #9, #52, #75, #86.

CRITICALNOT STARTED
Confirm DC ABCA mandated seed-to-sale platform

Confirm current requirement before any hardware purchased. Open Item #10.

CRITICALNOT STARTED
Security system vendor selection — ABCA-compliant CCTV & access control

DC ABCA requires 90-day minimum video retention, coverage of all entry/exit points, grow rooms, vault, and processing areas. Vendor must provide system spec for ABCA license application. Reached out to vendors.

CRITICALIN PROGRESS
20%
Cannabis business insurance — general liability, product liability, crop coverage

Required before operations begin. Need cannabis-specific carrier (e.g., Cannasure, Next Insurance, Burns & Wilcox). Reached out for quotes.

HIGHIN PROGRESS
15%
Permitting & Regulatory SubmissionsIN PROGRESS

DC ABCA pre-app, DCRA building/electrical/mechanical/plumbing permits, DC DOH kitchen plan review, DC Fire Marshal. Section 12.

0/9 (0%)
Schedule DC ABCA pre-application meeting

Confirms tier thresholds, canopy measurement method (~2,806 sq ft total: FR1:1,034 + FR2:1,034 + FR3:738), mandated seed-to-sale platform. Open Item #3.

CRITICALNOT STARTED
DC ABCA application submission

After floor plan complete. Components: dimensioned floor plan, security plan, odor mitigation plan, water usage plan, waste management plan, operating procedures. 90-180 day review.

CRITICALNOT STARTED
DCRA building permit — fit-out and change of use (no demolition)

Cornerstone Architecture as architect of record. 6-10 weeks after stamped drawings submitted. Open Item #88.

CRITICALNOT STARTED
DCRA electrical, mechanical, plumbing permits

Stamped drawings by Reno James. Concurrent with architectural permit.

CRITICALNOT STARTED
DC Fire Marshal — fire alarm and sprinkler permits

FPE stamped hydraulic calculations. NFPA 13 wet-pipe throughout. OH2 minimum in cultivation rooms.

HIGHNOT STARTED
AHJ written confirmation — 48" barn doors satisfy egress

Written confirmation required before panel order placed. Cornerstone to document basis of design for single exit per cultivation room. Open Items #58, #60.

CRITICALNOT STARTED
Confirm refrigeration panel fire rating — submit to DC DCRA

Polyurethane foam core must meet DC Building Code occupancy separation. Submit fire rating documentation with building permit. AHJ may require fire-rated panel. Open Items #59, #60.

CRITICALNOT STARTED
Schedule DC DOH pre-application meeting — edible kitchen

Schedule immediately — 4-8 week review cycle independent of ABCA track. Full A-124 equipment schedule submitted. Open Item #11.

HIGHNOT STARTED
Confirm DC DCRA CO2 bulk storage tank placement requirements

9,000-lb outdoor leased tank. DC DCRA and DC Fire Marshal confirmation for 6100 Chillum Place NE. Coordinate with Airgas or Air Liquide on delivery truck access. Section 12.5.

HIGHNOT STARTED
Pepco Service UpgradeIN PROGRESS

480V 3-phase 600A service upgrade — 326 kW load study, switchgear, 150-225 kVA transformer, Pepco coordination. Section 2.1-2.3.

0/7 (0%)
Initiate Pepco service upgrade — 326 kW, 600A 480V 3-phase

Begin immediately — 8-16 week lead. Existing 600A 120/208V service continues during wait. Open Item #1.

CRITICALIN PROGRESS
25%
Submit revised Pepco load study — 326 kW, 600A switchgear

Reno James to revise load study to 326 kW. 500-750 kVA pad-mount transformer request. Open Item #23.

CRITICALIN PROGRESS
45%
Pepco transformer installation — 500-750 kVA pad-mount

Revenue-grade meter with 15-min interval demand recording. Pepco installs pad-mount transformer at building exterior.

CRITICALNOT STARTED
Install 600A 480V main switchgear

Arc flash study required before energization. Label all gear per NFPA 70E. Service entrance location confirmed against as-builts.

CRITICALNOT STARTED
Install 150-225 kVA step-down transformer (480V → 120/208V)

Size precisely: 150-225 kVA for 600A service. 150°C aluminum wound, Energy Star, K-factor rated. Re-feed existing 120/208V panels. Open Item #31.

HIGHNOT STARTED
Audit all existing circuits on 120/208V panels

Reno James + Cornerstone. Document all existing circuits before any disconnection. Open Item #28.

HIGHNOT STARTED
Pepco energization and single-account final state

Existing 120/208V utility tap disconnected after step-down transformer confirmed operational. Open Items #26, #30.

HIGHNOT STARTED
Design & EngineeringIN PROGRESS

Cornerstone Architecture permit drawings (6-8 wks), Reno James MEP stamped drawings (6-8 wks), refrigeration panel layout lock. Section 12.6.

0/8 (0%)
Refrigeration Panel FabricationNOT STARTED

4" wall panels + 10" ceiling panels for FR1, FR2, FR3, Veg, Mom, Prop, Dry rooms — 8-12 week fabrication lead. Section 5.2, 7.1.

0/8 (0%)
Structural & Slab WorkNOT STARTED

Sump pit cutting, condensing unit roof point load PE letter, rooftop equipment zone mapping after solar field verify. Section 4.8, 5.6.

0/2 (0%)
Rough-In MEPNOT STARTED

Electrical conduit/wire, HVAC rough-in, plumbing rough-in, refrigeration line sets, CO2 distribution copper. Section 2-4.

0/13 (0%)
Refrigeration Panel InstallationNOT STARTED

FR1, FR2, FR3, Veg, Mom, Prop, Dry room 4" wall panels and 10" ceiling panels at 16 ft AFF. Section 5.2, 7.1.

0/6 (0%)
Grow Room Build-OutNOT STARTED

Epoxy floors, rolling bench rails, barn doors, UCL mounts, HPS/UCL fixture hang, Agrotek Controls nodes, OpenSprinkler. Section 2.6-2.9, 5.4, 6.4-6.6.

0/13 (0%)
MEP Trim-Out & CommissioningNOT STARTED

HVAC startup, Pepco energization, Agrotek Controls commissioning, OpenSprinkler/Aroya integration, CO2 startup, arc flash study. Section 3.1, 11.2.

0/6 (0%)
Upstairs Fit-OutNOT STARTED

Pre-roll room, packaging, kitchen (A-124 equipment), cure vault, office, common area. Section 10.

0/3 (0%)
DC ABCA Facility InspectionNOT STARTED

All systems operational, seed-to-sale platform live, full camera coverage, security plan active. Section 12.1.

0/2 (0%)
Manufacturing Fit-Out (Independent)MFGNOT STARTED

DOH Manufacturing Endorsement track — kitchen, upstairs processing, candy/chocolate A-124 program. Independent $150K budget. Section 10.4, 12.3.

0/4 (0%)