Permitting & Licensing

6100 Chillum Place NE · Zatty Cultivation LLC & Zatty Manufacturing LLC

Permits Approved

1/11

Critical Path

6

Blocked/Action Needed

0

Documents Ready

1/17

Critical: License Transfer Required Before Operations Begin

Licenses must be transferred from Zatty LLC to Zatty Cultivation LLC and Zatty Manufacturing LLC before any cultivation or manufacturing operations can commence. ABCA approval is required.

ABCA License Transfer Process
1

Pre-notification to ABCA

2

Application Submission

3

Background Checks

4

Facility Inspection

5

ABCA Board Approval

6

License Reissuance

Cultivator License Transfer
Not Started

Zatty LLC → Zatty Cultivation LLC

Step 1 of 6

Pre-notification to ABCA

Progress0%
1

Pre-notification to ABCA

Notify ABCA of intent to transfer license to new entity

2

Application Submission

Submit Change of Ownership application with all required documents

3

Background Checks

All principals of new entity complete ABCA background check process

4

Facility Inspection

ABCA inspector reviews facility for compliance with license conditions

5

ABCA Board Approval

Board votes on license transfer at public meeting

6

License Reissuance

New license issued to Zatty Cultivation LLC / Zatty Manufacturing LLC

Required Documents (1/17)

Medical Cannabis Business Transfer Consent Form (Notarized)
Executed LLC Agreement — Zatty Cultivation LLC
Certificate of Formation — Zatty Cultivation LLC (Delaware)
DC Foreign Entity Registration — Zatty Cultivation LLC
Principal Disclosure — Charles Meyer
Principal Disclosure — John Harkins
Principal Disclosure — Raj Deshmukh (Bodega & Caviar)
Facility Lease Agreement — 6100 Chillum Place NE
Floor Plan / Site Plan — Cultivation Areas
Security Plan — Cultivation Facility
METRC Integration Plan
Proof of Financial Responsibility / Insurance
Business License and Endorsement Application — Zatty Cultivation LLC
Business License Application Instructions and Checklists
Attestation Forms — Zatty Cultivation LLC
DC Tax Clearance Certificate — Zatty Cultivation LLC
Attorney/Agent Designation Form (Expediter)

ABCA change-of-ownership required. Process: (1) Notarize Transfer Consent Form, (2) Submit Business License & Endorsement Application, (3) Background checks on all principals, (4) 45-day public comment period, (5) ABC Board review & vote, (6) Facility inspection at 6100 Chillum Place NE, (7) License reissuance. PDR-1 zoning confirmed. Contact: [email protected] | (202) 442-4423. Must complete BEFORE cultivation operations begin.

Manufacturer License Transfer
Not Started

Zatty LLC → Zatty Manufacturing LLC

Step 1 of 6

Pre-notification to ABCA

Progress0%
1

Pre-notification to ABCA

Notify ABCA of intent to transfer license to new entity

2

Application Submission

Submit Change of Ownership application with all required documents

3

Background Checks

All principals of new entity complete ABCA background check process

4

Facility Inspection

ABCA inspector reviews facility for compliance with license conditions

5

ABCA Board Approval

Board votes on license transfer at public meeting

6

License Reissuance

New license issued to Zatty Cultivation LLC / Zatty Manufacturing LLC

Required Documents (0/14)

Medical Cannabis Business Transfer Consent Form — Manufacturing (Notarized)
Executed LLC Agreement — Zatty Manufacturing LLC
Certificate of Formation — Zatty Manufacturing LLC (Delaware)
DC Foreign Entity Registration — Zatty Manufacturing LLC
Principal Disclosure — Charles Meyer (Manufacturing)
Principal Disclosure — John Harkins (Manufacturing)
Manufacturing Facility Floor Plan
Manufacturing SOPs — Processing & Packaging
Equipment List — Manufacturing
Product Testing Protocol
Business License and Endorsement Application — Zatty Manufacturing LLC
Attestation Forms — Zatty Manufacturing LLC
DC Tax Clearance Certificate — Zatty Manufacturing LLC
Attorney/Agent Designation Form (Expediter)

ABCA change-of-ownership for manufacturing license. Can be filed concurrently with cultivator transfer. Type 1 (manufacturing only, no extraction) or Type 2 (manufacturing + extraction, requires DC Fire Marshal operational permit). PDR-1 zoning confirmed. 300-ft school/rec center buffer to be verified by expediter. Contact: [email protected]