Budget & Ledger

Double-entry accounting · $1.5M construction + $150K manufacturing

Total Budget
$1,500,000
Construction only
Committed
$42,417
3% of budget
Spent
$77,750
5% of budget
Remaining
$1,379,833
Available
Manufacturing Subset — Independent $150K BudgetSEPARATE
Budget
$150,000
Committed
$0
Spent
$0
Budget vs Committed vs Spent by Category
CAT-01CAT-02CAT-03CAT-04CAT-05CAT-06CAT-07CAT-08CAT-09CAT-10CAT-11CAT-12CAT-13CAT-14CAT-15CAT-16CAT-MFG$0K$60K$120K$180K$240K
  • Budget
  • Committed
  • Spent
Budget Categories Detail
CodeCategoryBudgetCommittedSpentRemainingUtilization
CAT-01Architecture & Engineering$90,000$9,750$19,750$80,250
22%
CAT-02Permits & Fees$50,000$0$0$50,000
0%
CAT-03Refrigeration Panels$160,000$0$0$160,000
0%
CAT-04Electrical$200,000$0$0$200,000
0%
CAT-05Mechanical / HVAC$230,000$0$0$230,000
0%
CAT-06Plumbing & Fertigation$90,000$0$0$90,000
0%
CAT-07Lighting$130,000$0$0$130,000
0%
CAT-08Controls & Automation$65,000$0$0$65,000
0%
CAT-09Security & Low Voltage$55,000$0$0$55,000
0%
CAT-10Fire Protection$40,000$0$0$40,000
0%
CAT-11Rolling Benches & UCL Mounting$50,000$0$0$50,000
0%
CAT-12Flooring$35,000$0$0$35,000
0%
CAT-13Equipment — Cultivation$35,000$0$0$35,000
0%
CAT-14Equipment — Processing$30,000$0$0$30,000
0%
CAT-15FF&E & Miscellaneous$25,000$0$0$25,000
0%
CAT-16Contingency (~5%)$65,000$0$0$65,000
0%
CAT-MFGManufacturing Subset$150,000$0$0$150,000
0%
CAT-OPSOperating Expenses (Pre-Revenue)$200,000$32,667$58,000$167,333
29%
TOTAL (Construction)$1,500,000$42,417$77,750$1,379,833